Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement |
133W13 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/THDC/NH-09/2022-23/PKG-III
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5653.00
Resanction Cost :
5653.00
Tentative Cost :
5653.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 5,653.00
Demand : 1,900.00
Allotment : 1,228.00
Exp in CFY : 1,228.00
Total Up to Date Exp : 1,228.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 65 %
Sanction on :
1 year 4 months ago
24 Feb 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Physical Peramenters