Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement |
133W14 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/THDC/NH-09/2022-23/PKG-I
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
19222.48
Resanction Cost :
19222.48
Tentative Cost :
19222.48
Exp. Upto Last Fy : 1,218.03
For CFY 2024-2025
Remaining : 18,004.45
Demand : 8,000.00
Allotment : 5,242.00
Exp in CFY : 0.00
Total Up to Date Exp : 1,218.03
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 74 %
Sanction on :
1 year 8 months ago
01 Nov 2022
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Physical Peramenters