Work Profile Report [133W15]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Job no. RW/UK/AP/NH-125(New NH 09)/2022-23/640
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7089.00
Resanction Cost :
7089.00
Tentative Cost :
3439.56
Saving
3649.44
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
7,089.00
Demand :
2,300.01
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 1 year 10 months ago
21 Feb 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
15 %
Tentative Completion date on : 7 months 2 days from now
27 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Assets :
Work not linked with IM
Bridges on The Basis of AI: