Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.725 | 1.725 | 1.725 | 0 |
140W14 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6082/III(2)/21-04(M.L.A.)/2017T.C.II
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3342.00
Resanction Cost :
3342.00
Tentative Cost :
3342.00
Exp. Upto Last Fy : 2,865.85
For CFY 2024-2025
Remaining : 476.15
Demand : 200.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2,865.85
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
2 years 7 months ago
15 Dec 2021
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अधिकांश काश्तकारों को प्रतिकर भुगतान कर दिया गया है। शेष कास्तकारों के प्रतिकर भुगतान की कार्यवाही गतिमान है। -- as on 13-Jul-2024
Physical Peramenters