Work Profile Report [140W15]

Development of infrastructure for Pilgrimage facilitation in Shree Badrinath Dham के अन्तर्गत Tourist Management Centre (TOURISTinterpretation centre + Command and control centre) Tourist arrival plaza at Badrinath (under PRASAD scheme)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 346/2-6-1147/2022-23 Dt 21.04.2022

TS Amount (lakhs) : 3165.8 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

3416.11

Resanction Cost :

3416.11

Tentative Cost :

3416.11

Exp. Upto Last Fy :

1,437.97

For CFY 2025-2026

Remaining :

1,978.14

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1,437.97

Construction Started

Sanction on : 3 years 1 month ago

21 Apr 2022

Physical Progress:

At start of FY 2025-2026 :

99 %

Up to Date :

99 %

Tentative Completion date on : 9 months 1 week ago

31 Aug 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Buildings
2
2
2
-

Remark

view all

Tourist Management Centre -STONE CLADDING, TRUSS ERECTION WORKS IN PROGRESS.
Arrival plaza-ARRIVAL PLAZA IS CURRENTLY BEING COMPROMISED FOR NECESSARY
MACHINE AND MATERIAL MOVEMENT FOR CIVIC AMNEITY BUILDING AND
TOURIST MANAGEMENT CENTRE.
-- as on 02-Jul-2024

Rating : 99

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: