Work Profile Report [140W5]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1644/VI(1)/2021-03(60)/2021
TS Amount (lakhs) : 2488.25 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2510.00
Resanction Cost :
2510.00
Tentative Cost :
2510.00
Exp. Upto Last Fy :
928.53
For CFY 2025-2026
Remaining :
1,581.47
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
928.53
Construction Started
Sanction on : 3 years 6 months ago
18 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
89 %
Up to Date :
90 %
Tentative Completion date on : 9 months 1 week ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
MASONRY WORKS & PLASTER WORKS IN PROGRESS. -- as on 02-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: