Work Profile Report [140W9]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2183/VI(1)/2021-03(109)/2021
TS Amount (lakhs) : 3222.88 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3222.88
Resanction Cost :
3222.88
Tentative Cost :
3222.88
Exp. Upto Last Fy :
179.76
For CFY 2025-2026
Remaining :
3,043.12
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
179.76
Construction Started
Sanction on : 3 years 5 months ago
13 Dec 2021
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
15 %
Tentative Completion date on : 5 months 1 week ago
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
COFFER DAM WASHED AWAY DUE TO RISE IN WATER LEVEL IS BEING REPAIRED FOR RESUMTION OF WORKS. -- as on 02-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: