Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 20.000 | -10 | 0.000 | 0.000 |
15W213 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शां0स0 5519/(1)/।।।(2)/10-06 (मु0म0घा0) /2010 दिनांक 15-10-2010
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
126.00
Resanction Cost :
126.00
Tentative Cost :
126.00
Exp. Upto Last Fy : 47.51
For CFY 2024-2025
Remaining : 78.49
Demand : 75.65
Allotment : 0.00
Exp in CFY : 5.30
Total Up to Date Exp : 52.81
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
13 years 9 months ago
15 Oct 2010
Tentative Completion date:
1 year 6 months ago
31 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 14: AIP Conservator
Bottelneck: no issue
कार्य पूर्ण। प्रभागीय वनाधिकारी के पत्रांक संख्या 817/12-1 दिनांक 22.08.2022 से एन0पी0वी0 धनराशि पुनः नदी दरों पर जमा कराने हेतु लिखा गया है , मार्च 2024 में बडी हुई दरों पर NPV की धनराशी वन विभाग के पक्ष में जमा की जा चुकी है। वर्तमान में नाप भूमि का मुआवजा वितरित किया जा रहा है। मार्ग पर कुछ काशनतकारों द्वारा मुआवजा कब्जाधारकों को वितरित किए हेतु मा० तहसीलदार न्ययालय में अग्रिम कार्यवाही तक रोक लगाने हेतु वाद दाखिल किया गया है। जिससे कारतकारों को ₹70.00 लाख का भुगतान नहीं किया जा सका। -- as on 11-Apr-2024
Physical Peramenters