Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
15W254 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6692/।।।(2)/11-83(प्रा्र0आ0)/2011 टी0सी0 दिनांक 22.12.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy : 0.32
For CFY 2024-2025
Remaining : 37.48
Demand : 37.45
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.32
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
12 years 6 months ago
22 Dec 2011
Tentative Completion date:
1 year 6 months ago
31 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मुआवजा वितरण की कार्यवाही की जा रही है। -- as on 06-Feb-2024
Physical Peramenters