Work Profile Report [15W267]

अडकिनी से जलतुुरी मोटर मार्ग के पिथौरागढ की प्रथम चरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 4784/।।।(2)/11-31(प्रा्र0आ0)/2011 दिनांक 14-12-2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

31.50

Resanction Cost :

31.50

Tentative Cost :

31.50

Exp. Upto Last Fy :

0.48

For CFY 2025-2026

Remaining :

31.02

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.48

Work completed

Sanction on : 13 years 6 months ago

14 Dec 2011

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 2 years 6 months ago

31 Dec 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
2.5
2.5
2.5
-

Remark

view all

विधिवत स्वीकृति अप्राप्त। पैड शौ किये जाने हेतु कार्यालय अधिशासी अभियन्ता के पत्रांक 1273/22 याता दिनांक 02.07.2024 द्वारा वन महानिरिक्षक (कैम्पा), भरत सरकार को पत्र प्रेषित। उक्त प्रकरण में मार्गदर्शन हेतु कार्यालय अधिशासी अभियन्ता के पत्रांक 1742/22 याता दिनांक 30.08.2024 द्वारा प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून को पत्र प्रेषित। -- as on 03-Apr-2025

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: