Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
15W366 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2189-1/।।।-2/13-60 प्रा0आ0/2012 दि022-03-2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
50.40
Exp. Upto Last Fy : 45.99
For CFY 2024-2025
Remaining : 4.41
Demand : 4.41
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 45.99
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 years 3 months ago
22 Mar 2013
Tentative Completion date:
1 year 6 months ago
31 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण मुआवजा वितरण की कार्यवाही कि जा रही है। -- as on 07-May-2023
Physical Peramenters