Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.5 | 0 |
15W739 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. No 1707(II) /III(2)/21 -43 (M.L.A.) T.C. -III dt 17.06.2021
TS Amount (lakhs) : 130.14 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
130.14
Resanction Cost :
130.14
Tentative Cost :
130.14
Exp. Upto Last Fy : 2.96
For CFY 2024-2025
Remaining : 127.18
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.96
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
3 years 1 month ago
17 Jun 2021
Tentative Completion date:
2 years 2 days ago
15 Jul 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work in progress -- as on 16-Dec-2022
Physical Peramenters