Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.45 | 3.45 | 0.000 | 3.45 | 0.000 | 0.000 |
15W746 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. No 1538 /III(2)/21 -43 (M.L.A.)/2017 T.C. dt 09.06.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
95.12
Resanction Cost :
95.12
Tentative Cost :
95.12
Exp. Upto Last Fy : 48.80
For CFY 2024-2025
Remaining : 46.32
Demand : 43.29
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 48.80
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 years 1 month ago
09 Jun 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 07-May-2023
Physical Peramenters