Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
15W766 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : File No. PWD2-CW/R/57/2022-III-2-Public Works Department (Computer No. 31646)
TS Amount (lakhs) : 36.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
36.32
Resanction Cost :
36.32
Tentative Cost :
36.32
Exp. Upto Last Fy : 13.21
For CFY 2024-2025
Remaining : 23.11
Demand : 22.98
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 13.21
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
1 year 6 months ago
20 Dec 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
0.950 किमी0 पहाड कटान का कार्य पूर्ण कर लिया गया है। शेष कार्य प्रगति में है। -- as on 04-Apr-2024
Physical Peramenters