Work Profile Report [15W770]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Computer No. I/57981/2022 Dated 24.08.2022
TS Amount (lakhs) : 61.62 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
61.62
Resanction Cost :
61.62
Tentative Cost :
61.62
Exp. Upto Last Fy :
7.39
For CFY 2024-2025
Remaining :
54.23
Demand :
54.17
Allotment :
54.23
Exp in CFY :
29.17
Total Up to Date Exp :
36.56
Work completed
Sanction on : 2 years 3 months ago
27 Aug 2022
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष है । -- as on 06-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: