Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
15W791 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5085/III(2)/18-43 (MLA)/2017 T.C. Dated 16 October 2018
TS Amount (lakhs) : 712.62 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
712.62
Resanction Cost :
712.62
Tentative Cost :
712.62
Exp. Upto Last Fy : 10.05
For CFY 2024-2025
Remaining : 702.57
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 10.05
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 9 months ago
16 Oct 2018
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
दिनांक 31.03.24 को संशोधित बढ़ी हुई दरों पर NPV की धनराशि वन विभाग के पक्ष में RTGS द्वारा जमा की जा चुकी है। इस कार्यालय के पत्रांक 63 /कैंप 22 याता दिनांक 22 -04 -2024 द्वारा विधिवत स्वीकृति हेतु अनुस्मरण पत्राचार किया गया है। स्वीकृति अपेक्षित है। मूल कार्य 10.00 किमी0 लम्बाई में पहाड़ कटान व दीवार स्कपर निर्माण का कार्य पूर्ण। निर्माण के उपरान्त 3 वर्षीय अनुरक्षण का कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters