Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.85 | 7.85 | 7.85 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
15W808 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
123.09
Resanction Cost :
123.09
Tentative Cost :
123.09
Exp. Upto Last Fy : 42.25
For CFY 2024-2025
Remaining : 80.84
Demand : 80.84
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 42.25
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्वों का भुगतान शेष है। -- as on 11-Jun-2024
Physical Peramenters