Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.35 | 1.35 | 1.350 | 0 | 0.000 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
15W845 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-CW/R/18/2023-III-2-Public Works Department E File no. 48456
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.38
Resanction Cost :
35.38
Tentative Cost :
35.38
Exp. Upto Last Fy : 20.42
For CFY 2024-2025
Remaining : 14.96
Demand : 16.34
Allotment : 0.00
Exp in CFY : 13.52
Total Up to Date Exp : 33.94
Work completed
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष है । -- as on 06-Jun-2024
Physical Peramenters