Work Profile Report [15W846]
Tenders
Project Activities
alerts
Administrative Approval Detail : शासन का पत्रांक संख्या-2451/।।।(2)/23-01(प्रा0आ0)/2019 दिनांक 21 जुलाई, 2023
TS Amount (lakhs) : 824.45 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
850.19
Resanction Cost :
850.19
Tentative Cost :
824.45
Saving
25.74
Exp. Upto Last Fy :
448.40
For CFY 2024-2025
Remaining :
401.79
Demand :
375.63
Allotment :
188.45
Exp in CFY :
188.45
Total Up to Date Exp :
636.85
Construction Started
Sanction on : 1 year 5 months ago
21 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
90 %
Tentative Completion date on : 7 months 6 days ago
18 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 25.74 has been recorded as expected cost of work reduced from 850.19 to 824.45 . -- as on 06-Aug-2024