Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 34 | 34 | 34 | 0 | ||
Jobs | 1 | 1 | 1 | 0 |
15W848 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन का पत्रांक संख्या-2451/।।।(2)/23-01(प्रा0आ0)/2019 दिनांक 21 जुलाई, 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.00
Resanction Cost :
159.00
Tentative Cost :
159.00
Exp. Upto Last Fy : 48.65
For CFY 2024-2025
Remaining : 110.35
Demand : 110.35
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 48.65
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 90 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
1 month 3 weeks ago
24 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work in progress -- as on 14-Mar-2024
Physical Peramenters