Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
15W858 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No. 55210 Lok Nirman Anubhag-2 dt 11-10-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.75
Resanction Cost :
3.75
Tentative Cost :
3.75
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 3.65
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 months 6 days ago
11 Oct 2023
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण का कार्य प्रगति में है। -- as on 05-Apr-2024
Physical Peramenters