Work Profile Report [15W859]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No. 53127 Lok Nirman Anubhag-2 dt 30-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
759.30
Resanction Cost :
759.30
Tentative Cost :
759.30
Exp. Upto Last Fy :
304.26
For CFY 2025-2026
Remaining :
455.04
Demand :
455.04
Allotment :
282.13
Exp in CFY :
282.13
Total Up to Date Exp :
586.39
Construction Started
Sanction on : 1 year 9 months ago
30 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
75 %
Tentative Completion date on : 2 weeks 5 days from now
12 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
525 मीटर लम्बाई में नाले का कार्य पूर्ण कर लिया गया है। शेष कार्य प्रगति में है। -- as on 14-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: