Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
15W863 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No. 53524 Lok Nirman Anubhag-2 dt 26-09-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.01
Resanction Cost :
58.01
Tentative Cost :
58.01
Exp. Upto Last Fy : 14.27
For CFY 2024-2025
Remaining : 43.74
Demand : 43.74
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 14.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 75 %
Sanction on :
9 months 3 weeks ago
26 Sep 2023
Tentative Completion date:
4 months 4 weeks from now
15 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वर्तमान में जी1,जी2,जी3 का कार्य पूर्ण। पी0सी0 का कार्य मौसम अनुकूल होने पर पूर्ण कर लिया जायेगा। -- as on 28-Jun-2024
Physical Peramenters