Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.3 | 9.3 | 0.000 | 9.3 | 9.300 | 0.000 |
15W864 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No. 62449 Lok Nirman Anubhag-2 dt 29-11-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
307.21
Resanction Cost :
307.21
Tentative Cost :
307.21
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 307.11
Demand : 307.11
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 90 %
Sanction on :
7 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
4 months 4 weeks from now
15 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work in Progress -- as on 05-Apr-2024
Physical Peramenters