Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
16W130 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 7234/।।।(2)/11-117(प्रा0आ0)/2011 दि0 22.12.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.74
Resanction Cost :
37.74
Tentative Cost :
37.74
Exp. Upto Last Fy : 0.45
For CFY 2024-2025
Remaining : 37.29
Demand : 0.25
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.45
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
12 years 6 months ago
22 Dec 2011
Tentative Completion date:
6 years 3 months ago
31 Mar 2018
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
दिनांक 20.06.24 को डी एम कार्यालय पिथौरागढ़ से नक्शे प्राप्त । -- as on 05-Jul-2024
Physical Peramenters