Work Profile Report [16W138]

नाचनी बांसबगड मोटर मार्ग के किमी0 3 से बाथीगूठ सुन्धरीनाग मोटर मार्ग का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 6606/।।।(2)/11 -123(प्रा0आ0)/2011 दि0 24.12.2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

125.80

Resanction Cost :

125.80

Tentative Cost :

125.80

Exp. Upto Last Fy :

4.26

For CFY 2024-2025

Remaining :

121.54

Demand :

6.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

4.26

Work completed

Sanction on : 12 years 10 months ago

24 Dec 2011

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 7 years 7 months ago

31 Mar 2017

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
10
10
-

Remark

view all

भूमि प्रतिकर प्रस्ताव गठन की कार्यवाही गतिमान। -- as on 20-Jul-2024

Rating : 80

Forest Case Pending At : 21: Final

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand