Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 |
16W138 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6606/।।।(2)/11 -123(प्रा0आ0)/2011 दि0 24.12.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
125.80
Resanction Cost :
125.80
Tentative Cost :
125.80
Exp. Upto Last Fy : 4.26
For CFY 2024-2025
Remaining : 121.54
Demand : 6.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
12 years 6 months ago
24 Dec 2011
Tentative Completion date:
7 years 3 months ago
31 Mar 2017
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
वनभूमि की विधिवत स्वीकृति प्राप्त। -- as on 21-Feb-2024
Physical Peramenters