Work Profile Report [16W20]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 764/।।।-2/08-65 (प्रा0आ0)/07 टीसी दि0 24.3.08
TS Amount (lakhs) : 220.5 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
220.50
Resanction Cost :
220.50
Tentative Cost :
169.05
Saving
51.45
Exp. Upto Last Fy :
198.82
For CFY 2025-2026
Remaining :
21.68
Demand :
4.40
Allotment :
4.38
Exp in CFY :
4.38
Total Up to Date Exp :
203.21
In Maintenance After Completion
Sanction on : 17 years 8 months ago
24 Mar 2008
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 1 month ago
27 Oct 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में कार्य अनुरक्षण के अन्तर्गत है। -- as on 27-Nov-2025
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Steel Girder Bridge (Sh-11) Km 186.825