Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
16W305 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2724/।।।(2)/15-05(मु0मं0घो0)/15 दिनांक 23-04-2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
83.25
Resanction Cost :
83.25
Tentative Cost :
83.25
Exp. Upto Last Fy : 7.30
For CFY 2024-2025
Remaining : 75.95
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.30
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
9 years 2 months ago
23 Apr 2015
Tentative Completion date:
6 years 3 months ago
31 Mar 2018
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जिलाधिकारी पिथौरागढ़ द्वारा सिविल वन भूमि की स्वीकृति प्राप्त। भूमि प्रतिकर भुगतान शेष प्रथम चरण के अन्य कार्य पूर्ण। -- as on 06-Jan-2024
Physical Peramenters