Work Profile Report [16W338]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : शा0सं0 7209/।।।(2)/15-09(प्रा0आ0/2014 दिनांक 17.10.2015
TS Amount (lakhs) : 492.98 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
323.65
Resanction Cost :
323.65
Tentative Cost :
303.65
Saving
20.00
Exp. Upto Last Fy :
270.95
For CFY 2025-2026
Remaining :
52.70
Demand :
32.70
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
270.95
Work completed
Sanction on : 10 years 1 month ago
17 Oct 2015
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 months ago
15 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 20 has been recorded as expected cost of work reduced from 323.65 to 303.65 . -- as on 02-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand