Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 100 | 100 | 100 | 0 |
16W341 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 428/।।।(2)/16-14(मु0मं0घो0)/2015 दिनांक 23.01.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 5.00 Lacs
Resanction Cost : 5.00 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 4.90 Lacs
Demand : 0.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
8 years 3 months ago
23 Jan 2016
Tentative Completion date:
6 years 1 month ago
31 Mar 2018
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
भूगर्भीय आख्या प्राप्त स्थल चयन का कार्य प्रगति पर। -- as on 06-Jul-2021
Physical Peramenters