Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
16W351 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 428/।।।(2)/16-14(मु0मं0घो0)/2015 दिनांक 23.01.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.00
Resanction Cost :
21.00
Tentative Cost :
21.00
Exp. Upto Last Fy : 0.57
For CFY 2024-2025
Remaining : 20.43
Demand : 0.30
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.57
Survey work done
Physical Progress:
At start of FY 2024-2025 : 27 %
Up to Date : 27 %
Sanction on :
8 years 5 months ago
23 Jan 2016
Tentative Completion date:
6 years 3 months ago
31 Mar 2018
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
पेड़ो की सूची उपलब्ध कराने हेतु इस कार्यालय के पत्रांक 73/1सी दिनांक 27.06.2024 द्वारा रेंजर मुनस्यारी को पत्र प्रेषित वनभूमि प्रस्ताव खण्ड स्तर पर गठित किया जा रहा है। -- as on 05-Jul-2024
Physical Peramenters