Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
16W358 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 428/।।।(2)/16-14(मु0मं0घो0)/2015 दिनांक 23.01.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 35.40 Lacs
Resanction Cost : 35.40 Lacs
Exp. Upto Last Fy : 0.27 Lacs
For CFY 2024-2025
Remaining : 35.13 Lacs
Demand : 0.20 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.27 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
8 years 3 months ago
23 Jan 2016
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 08: State Government
Bottelneck: no issue
वन भूमि प्रस्ताव आनलाइन राज्य सरकार स्तर पर। -- as on 30-Apr-2024
Physical Peramenters