Work Profile Report : 16W358
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 428/।।।(2)/16-14(मु0मं0घो0)/2015 दिनांक 23.01.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.40
Resanction Cost :
35.40
Tentative Cost :
35.40
Exp. Upto Last Fy :
0.28
For CFY 2025-2026
Remaining :
35.12
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.28
Alignment Approved
Sanction on : 10 years 2 weeks ago
23 Jan 2016
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 1 year 10 months from now
31 Dec 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में वनभूमि प्रस्ताव नोडल स्तर से आपत्ति के कारण डी0एफ0ओ0 स्तर पर लम्बित। -- as on 06-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: