Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.6 | 7.6 | 7.6 | 0 |
16W371 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 842/।।।(2)/16-60(प्रा0आ0)/2015 दिनांक 16.02.2016
TS Amount (lakhs) : 380.95 Lacs
Financial Detail
Sanction Cost : 380.95 Lacs
Resanction Cost : 398.93 Lacs
Exp. Upto Last Fy : 322.30 Lacs
For CFY 2024-2025
Remaining : 76.63 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 322.30 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 3 months ago
16 Feb 2016
Tentative Completion date:
2 years 3 months ago
28 Jan 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 06-Jul-2021
Physical Peramenters