Work Profile Report [16W372]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 842/।।।(2)/16-60(प्रा0आ0)/2015 दिनांक 16.02.2016
TS Amount (lakhs) : 299.89 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
299.89
Resanction Cost :
312.93
Tentative Cost :
299.89
Saving
13.04
Exp. Upto Last Fy :
242.21
For CFY 2024-2025
Remaining :
70.72
Demand :
10.00
Allotment :
5.00
Exp in CFY :
0.00
Total Up to Date Exp :
242.21
In Maintenance After Completion
Sanction on : 8 years 9 months ago
16 Feb 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 5 months ago
15 Jun 2021
Actual Completion Date : 3 years 4 months ago
30 Jun 2021
Physical Linear Components
Remark
PCR sent To CE Vide SE letter No 4854/480 C-03/2023 Dated 28-08-2023 -- as on 20-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand