Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
16W372 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 842/।।।(2)/16-60(प्रा0आ0)/2015 दिनांक 16.02.2016
TS Amount (lakhs) : 299.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
299.89
Resanction Cost :
312.93
Tentative Cost :
299.89
Saving
13.04
Exp. Upto Last Fy : 242.21
For CFY 2024-2025
Remaining : 70.72
Demand : 10.00
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 242.21
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 5 months ago
16 Feb 2016
Tentative Completion date:
3 years 1 month ago
15 Jun 2021
Actual Completion Date:
3 years 2 weeks ago
30 Jun 2021
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। In Principal approval -- as on 02-Jan-2024
Physical Peramenters