Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
16W39 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 827/।।।-2/06-76 (प्रा0आ0) /05 टीसी दि0 28.3.06
TS Amount (lakhs) : 93.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
93.70
Resanction Cost :
93.70
Tentative Cost :
93.70
Exp. Upto Last Fy : 70.94
For CFY 2024-2025
Remaining : 22.76
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 70.94
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
18 years 3 months ago
28 Mar 2006
Tentative Completion date:
7 years 3 months ago
06 Apr 2017
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: Alignment Dispute
2.00 किमी0पहाड़ कटान पूर्ण 2.00 किमी0पार्ट।। का काय पूर्ण। समरेखन में विवाद कुछ ग्रामीणों द्वारा समरेखन बदलने के लिए कहा जा रहा है। मोटर मार्ग की विधिवत स्वीकृति उत्तराखंड शाशन के पत्रांक जी0आई0 2437/7-1-2010-600 (3484)/2010 दिनांक 30-10-2010 द्वारा प्राप्त। -- as on 02-Jan-2024
Physical Peramenters