Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 70 | 70 | 0.000 | 70 | 70.000 | 0.000 |
16W443 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Ranibagh Bridge Bangapani
Administrative Approval Detail : शा0सं0 2472/।।।(2)/ 16-42(एम0एल0ए0)/2016 दिनांक 09.12.2016
TS Amount (lakhs) : 786.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
786.76
Resanction Cost :
786.76
Tentative Cost :
786.76
Exp. Upto Last Fy : 519.67
For CFY 2024-2025
Remaining : 267.09
Demand : 176.00
Allotment : 0.00
Exp in CFY : 0.81
Total Up to Date Exp : 520.49
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 82 %
Sanction on :
7 years 7 months ago
09 Dec 2016
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सेतु के इरेक्शन का कार्य प्रगति पर। -- as on 13-Jul-2024
Physical Peramenters