Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | 0 | 0 |
Span of Bridges [m] | 80 | 80 | 80.000 | 0 | 0.000 | 0.000 |
16W486 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: 24 Mtr Span Steel Girder Dhapua Gad
Administrative Approval Detail : शा0सं0 1156/।।।(2)/14-68(प्रा0आ0)/2013 दिनांक 22.02.2014
TS Amount (lakhs) : 554.86 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
554.86
Resanction Cost :
554.86
Tentative Cost :
554.86
Exp. Upto Last Fy : 438.43
For CFY 2024-2025
Remaining : 116.43
Demand : 23.00
Allotment : 0.00
Exp in CFY : 23.06
Total Up to Date Exp : 461.49
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 4 months ago
22 Feb 2014
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष्। -- as on 04-Apr-2024
Physical Peramenters