Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
16W493 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1105/।।।(2)/18-43(एम0एल0ए0)/2017 दिनांक 09.03.2018।
TS Amount (lakhs) : 235.01 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
235.01
Resanction Cost :
235.01
Tentative Cost :
235.01
Exp. Upto Last Fy : 223.78
For CFY 2024-2025
Remaining : 11.23
Demand : 5.00
Allotment : 2.00
Exp in CFY : 2.00
Total Up to Date Exp : 225.78
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 4 months ago
09 Mar 2018
Tentative Completion date:
3 years 8 months ago
21 Oct 2020
Actual Completion Date:
4 years 3 months ago
01 Apr 2020
Remark
Bottelneck: no issue
कार्य पूण। दायित्व शेष। -- as on 30-Nov-2020
Physical Peramenters