Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
16W493 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1105/।।।(2)/18-43(एम0एल0ए0)/2017 दिनांक 09.03.2018।
TS Amount (lakhs) : 235.01 Lacs
Financial Detail
Sanction Cost : 235.01 Lacs
Resanction Cost : 235.01 Lacs
Exp. Upto Last Fy : 223.78 Lacs
For CFY 2024-2025
Remaining : 11.23 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 2.00 Lacs
Total Up to Date Exp : 225.78 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 2 months ago
09 Mar 2018
Tentative Completion date:
3 years 6 months ago
21 Oct 2020
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूण। दायित्व शेष। -- as on 30-Nov-2020