Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 7 | 7 | 0 |
16W518 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3279/।।।(2)/19-45(एम0एल0ए0)/2017 टी.सी.-। दिनांक 04.09.2019।
TS Amount (lakhs) : 41.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.26
Resanction Cost :
41.26
Tentative Cost :
41.26
Exp. Upto Last Fy : 0.74
For CFY 2024-2025
Remaining : 40.52
Demand : 0.15
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.74
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 51 %
Up to Date : 51 %
Sanction on :
4 years 10 months ago
04 Sep 2019
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
डी एफ ओ पिथौरागढ़ के पत्रांक 8247/12-1 दिनांक 18.06.2024 द्वारा प्रस्ताव आपत्तियां में प्राप्त। आपत्रियो के निराकरण के अन्तर्गत प्रस्ताव रेंजर बेरीनाग को प्रेषित। -- as on 05-Jul-2024
Physical Peramenters