Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 7 | 7 | 0 |
16W518 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3279/।।।(2)/19-45(एम0एल0ए0)/2017 टी.सी.-। दिनांक 04.09.2019।
TS Amount (lakhs) : 41.26 Lacs
Financial Detail
Sanction Cost : 41.26 Lacs
Resanction Cost : 41.26 Lacs
Exp. Upto Last Fy : 0.74 Lacs
For CFY 2024-2025
Remaining : 40.52 Lacs
Demand : 0.15 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.74 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 51 %
Up to Date : 51 %
Sanction on :
4 years 8 months ago
04 Sep 2019
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
संयुक्त निरीक्षण किया जा चुका है। वनभूमि प्रस्ताव आफलाईन गठित कर अधिशासी अभियन्ता के पत्रांक 277/3सी0 दिनांक 02.02.2024 को प्रभागीय वनाधिकारी वन प्रभाग पिथौरागढ़ को हस्ताक्षर हेतु प्रेषित। -- as on 30-Apr-2024
Physical Peramenters