Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
16W538 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Boragaon Bridge
Administrative Approval Detail : 1544/।।।(2)/21-43 (एम0एल0ए0)/2017 टी0सी0 ।।। दि0 09.06.2021
TS Amount (lakhs) : 157.98 Lacs
Financial Detail
Sanction Cost : 157.98 Lacs
Resanction Cost : 157.98 Lacs
Exp. Upto Last Fy : 144.93 Lacs
For CFY 2024-2025
Remaining : 13.05 Lacs
Demand : 8.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 144.93 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
09 Jun 2021
Tentative Completion date:
4 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status ---
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष् -- as on 16-Dec-2023
Physical Peramenters