Work Profile Report [16W568]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 3118 (।)/।।।(2)/21-45(एम0एल0ए0)/2017 दिनांक 24.08.2021
TS Amount (lakhs) : 203.29 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
203.29
Resanction Cost :
203.29
Tentative Cost :
203.29
Exp. Upto Last Fy :
171.61
For CFY 2024-2025
Remaining :
31.68
Demand :
27.00
Allotment :
15.00
Exp in CFY :
14.88
Total Up to Date Exp :
186.49
Work completed
Sanction on : 3 years 2 months ago
24 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 19-Aug-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand