Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.75 | 3.75 | 3.75 | 0 |
16W571 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5236/।।।(2)/21-48(प्रा0आ0)/2018 दिनांक 28 अक्टूबर 2021
TS Amount (lakhs) : 250.06 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
250.06
Resanction Cost :
250.06
Tentative Cost :
250.06
Exp. Upto Last Fy : 242.37
For CFY 2024-2025
Remaining : 7.69
Demand : 4.00
Allotment : 4.00
Exp in CFY : 0.00
Total Up to Date Exp : 242.37
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
28 Oct 2021
Tentative Completion date:
8 months 2 weeks ago
31 Oct 2023
Actual Completion Date:
1 year 3 months ago
01 Apr 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 18-Jul-2023
Physical Peramenters