Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
16W585 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल सं0- 31215 दिनांक 27 जुलाई 2022
TS Amount (lakhs) : 148.06 Lacs
Financial Detail
Sanction Cost : 148.06 Lacs
Resanction Cost : 148.06 Lacs
Exp. Upto Last Fy : 103.89 Lacs
For CFY 2024-2025
Remaining : 44.17 Lacs
Demand : 27.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 103.89 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 9 months ago
27 Jul 2022
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 08-Nov-2023
Physical Peramenters