Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
16W585 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल सं0- 31215 दिनांक 27 जुलाई 2022
TS Amount (lakhs) : 148.06 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
148.06
Resanction Cost :
148.06
Tentative Cost :
148.06
Exp. Upto Last Fy : 103.89
For CFY 2024-2025
Remaining : 44.17
Demand : 27.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 103.89
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 11 months ago
27 Jul 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 08-Nov-2023
Physical Peramenters