Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 26 | 26 | 26 | 0 | ||
No of Bridges | 5 | 5 | 5 | 0 | ||
Span of Bridges [m] | 142 | 142 | 142 | 0 |
16W6 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5763/।।।(2)/।।-58(सा0-मु0मं0घो0)/2011 दि0 1.11.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
337.72
Resanction Cost :
337.72
Tentative Cost :
337.72
Exp. Upto Last Fy : 84.08
For CFY 2024-2025
Remaining : 253.64
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 84.08
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
12 years 8 months ago
01 Nov 2011
Tentative Completion date:
7 years 3 months ago
31 Mar 2017
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य 13 किमी0 में पूर्ण। भूमि प्रतिकर अवशेष। ग्रामीणों द्वारा किमी0 14 से आगे विवाद किया जा रहा है। विवाद सुलझाने हेतु सहायक अभियन्ता केे पत्रांक 84/1सी0 दि0 16.05.2023 द्वारा ग्राम प्रधान उच्छेती एवं ढीलम को पत्र प्रेषित। -- as on 13-Apr-2024
Physical Peramenters