Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 0.000 | 0.000 |
16W616 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : Govt. ई फाईल संख्या 51161 दिनांक 31 मार्च 2023 and 1155 आर-16. आर आई डी एफ -XXIX122 आईएमसी-21-08-2023
TS Amount (lakhs) : 85.4 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
85.40
Resanction Cost :
85.40
Tentative Cost :
85.40
Exp. Upto Last Fy : 22.46
For CFY 2024-2025
Remaining : 62.94
Demand : 60.00
Allotment : 60.00
Exp in CFY : 0.91
Total Up to Date Exp : 23.37
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 60 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
2 months 1 week from now
25 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इन्टरकोट बिछाने का कार्य पूर्णं। टाॅप कोट हेतु Stone Balast एकत्रित। -- as on 04-Jul-2024
Physical Peramenters