Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
16W617 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण विभाग अनुभाग-2 के ई फाईल संख्या 50746 दिनांक 31 मार्च,2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.60
Resanction Cost :
29.60
Tentative Cost :
29.60
Exp. Upto Last Fy : 26.62
For CFY 2024-2025
Remaining : 2.98
Demand : 2.98
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 26.62
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
5 months 2 weeks ago
31 Jan 2024
Actual Completion Date:
6 months 6 days ago
11 Jan 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 10-Apr-2024
Physical Peramenters