Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
16W626 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लोक निर्माण विभाग उत्तराखण्ड देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
254.85
Resanction Cost :
254.85
Tentative Cost :
254.85
Exp. Upto Last Fy : 81.58
For CFY 2024-2025
Remaining : 173.27
Demand : 30.00
Allotment : 35.00
Exp in CFY : 4.27
Total Up to Date Exp : 85.86
Work completed
Physical Progress:
At start of FY 2024-2025 : 12 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 weeks 1 day from now
09 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य मुख्य अभियन्ता URRDA उत्तराखण्ड देहरादून के पत्रांक 2448/II/ (XIX)-2/ITCO/URRDA/23 दिनांक 02.03.2024 द्वारा पी0एम0जी0एस0वाई0 फेज-।।। में स्वीकृत होने के कारण इस खण्ड द्वारा पी0सी0 का कार्य नहीं कराया जा रहा है। अनुबन्ध का अन्तिमीकरण एवं पी0एम0जी0एस0वाई0 को हस्तान्तरण की कार्यवाही गतिमान। -- as on 14-Jun-2024
Physical Peramenters