Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 |
16W626 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लोक निर्माण विभाग उत्तराखण्ड देहरादून के पत्रांक 895/07 याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 254.85 Lacs
Resanction Cost : 254.85 Lacs
Exp. Upto Last Fy : 81.58 Lacs
For CFY 2024-2025
Remaining : 173.27 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 81.58 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 12 %
Up to Date : 40 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
2 months 2 weeks from now
09 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 16-Dec-2023
Physical Peramenters