Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 9 | 0 |
16W655 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 देहरादून के ई फाईल सं0 48456 दिनांक 21.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 216.20 Lacs
Resanction Cost : 216.20 Lacs
Exp. Upto Last Fy : 55.47 Lacs
For CFY 2024-2025
Remaining : 160.73 Lacs
Demand : 155.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 55.47 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 30 %
Sanction on :
8 months 4 weeks ago
21 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 07-Jan-2024
Physical Peramenters