Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.6 | 1.6 | 1.6 | 0 |
16W656 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : त्तराखण्ड शासन लोक निर्माण अनुभाग-2 देहरादून के ई फाईल संख्या 53524 दिनांक 10 अक्टूबर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
99.01
Resanction Cost :
99.01
Tentative Cost :
99.01
Exp. Upto Last Fy : 2.47
For CFY 2024-2025
Remaining : 96.54
Demand : 90.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.47
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 25 %
Sanction on :
9 months 1 week ago
10 Oct 2023
Tentative Completion date:
3 months 2 weeks from now
05 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग का कार्य प्रगति पर। -- as on 28-Jun-2024