Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.95 | 0.95 | 0.000 | 0.95 | 0.000 | 0.000 |
16W660 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लो0नि0वि0, अनुभाग 2 के ई0 फाईल संख्या-64236 दिनांक 28 नवम्बर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
55.12
Resanction Cost :
55.12
Tentative Cost :
55.12
Exp. Upto Last Fy : 12.59
For CFY 2024-2025
Remaining : 42.53
Demand : 38.00
Allotment : 7.46
Exp in CFY : 7.46
Total Up to Date Exp : 20.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 30 %
Sanction on :
7 months 2 weeks ago
28 Nov 2023
Tentative Completion date:
3 months 3 weeks from now
14 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 04-Mar-2024